Hindalco Industries Limited
Aditya Aluminium · Smelter · Candidate projects · this year · simulated data
AP

1Business objective, this yearfrom the policy deployment: take 10 crore out of the cost of production at the smelter

Capital this year2.5 crore

most years, about three of these

Behind E's 3.0

Baseline39hours a month, where the loss has beenAddressable32seven hours of planned maintenance stayTarget11once the two causes attacked are goneRemoved28hours a month, 336 a year

336 h × 0.9 lakh an hour = 3.0 crore a year

Funded

2.2 of 2.5 crore

8.7 crore of loss removed a year
of the 10 crore the objective asks for

Candidate A

Cost of loss

what winning is worth

216.9

₹ lakh a year

Remove the loss, keep the money. The number comes from the loss and its certified cost, nothing else.

Cost of project

what winning will take

2.0

₹ crore, one off

the proposal: a new feed conveyor
against the blockage cause

  • ● five days of potline shutdown
  • ● the feed system team

You funded

A, B, C

The evidence supports